Aggreko completes the largest flare gas to power project to date in the Middle East
Aggreko is proud to announce we have completed commissioning of the largest flare gas to power project in the Middle East to date at 165 MW capacity. The plant is situated nearby the Saqala Field, Garmain block, South East Kurdistan.
The 165 MW modular power plant has run at full capacity for 72 hours in the project’s final site acceptance test (SAT), marking successful on-time, on-budget delivery. The plant is run on approximately 40 million square cubic feet (SCF) per day of associated petroleum gas (APG) from the Saqala Field, saving 840 tonnes of CO2 per day, and cutting flaring by a third.
Delivered over the course of 2020-2021 against the backdrop of the pandemic, the project was conceived and executed in close collaboration with Kurdistan’s Ministry of National Resources (MNR) and Ministry of Electricity (MOE).
Aggreko also delivered a new 6km gathering pipeline to transport the APG to the power plant, and upgraded 7km of 33 kV and 33km of 132 kV overhead cables to new high tensile low sage (HTLS) conductors in order for the local distribution grid to handle the new power plant’s full output.
Ahmed Mufti, Kurdistan Regional Government’s Deputy Minister of Natural Resources (MNR) said, “We worked with Aggreko to provide a creative solution to convert flare gas to power in a way that directly benefits the local population and the regional in general, while creating a positive environmental impact and improving air quality."
Phil Burns, Managing Director for Aggreko Middle East, comments: “Kurdistan’s Regional Government has been forward-thinking in looking for ways to capture and convert gas that would otherwise be flared, to unlock production and power the local economy. We are extremely proud to have worked with the Ministries to deliver the Middle East’s largest flare gas to power project to date, while upgrading the local infrastructure to the lasting benefit of the community and businesses it serves.”
The project is now contracted to run for four years, delivering power 24/7/365. Built using 192 MW of modular gas generators, the plant can easily be scaled up or down in response to changing gas volumes. Approximately 60 Aggreko engineers have delivered the project, with 80 local jobs created directly and indirectly for the site's delivery and ongoing operation, including 44 local nationals who have already commenced Aggreko's official training scheme.
News Category:
-
Lummus Technology completes startup of electric heater demonstration unit
Lummus Technology, a global provider of process technologies and value-driven energy solutions, announced the successful startup of its SRT-eTM commercial demonstration ...
03-04-2025
-
Clariant announces the successful startup of MegaMax™ 900 catalyst
Clariant, a sustainability-focused specialty chemical company, today announced the successful startup of its MegaMax 900 methanol synthesis catalyst at European Energy’s ...
03-04-2025
-
Burckhardt Compression, a global leader in reciprocating compressor technology, has won a significant order for Digital Monitoring Services in Saudi Arabia. The order ...
03-04-2025
-
Brookfield Infrastructure announces the acquisition of Colonial Enterprises
Brookfield Infrastructure Partners L.P. and its institutional partners reached a definitive agreement to acquire 100% of the world-class midstream asset portfolio Colonial ...
03-04-2025
-
DB Schenker to boost adoption of Neste MY Renewable Diesel in Singapore and Asia-Pacific
Neste and DB Schenker, one of the world’s leading logistics service providers, have collaborated to work towards expanding DB Schenker’s adoption of Neste MY Renewable ...
02-04-2025
-
Stockholm Exergi to begin building one of the world's largest carbon capture projects
With technology licensed from CATACARB to proceed building one of the world's largest facilities for capture and permanent storage of carbon dioxide. Operations ...
01-04-2025
-
VARO announces transformative acquisition of Preem AB
VARO Energy has today reached agreement to acquire Preem Holding AB and Preem AB through the purchase of 100% of the share capital of the parent company, Corral Petroleum ...
31-03-2025
-
TotalEnergies and partners launch 2nd phase of Northern Lights CCS project
TotalEnergies and its partners, Equinor and Shell, announce the Final Investment Decision of the second phase of the Northern Lights development, which will increase ...
27-03-2025
-
Eni and Saipem extend collaboration agreement in biorefining
Eni and Saipem extended the collaboration agreement signed between the two companies in November 2023 to combine their respective skills and specialisations in the industrial ...
27-03-2025
-
BASF and Forestal agreement to advance e-methanol production
BASF and Forestal de Atlántico S.A. have signed an early disclosure agreement aimed at advancing the production of e-methanol through carbon capture solutions. Under ...
26-03-2025