Aggreko completes the largest flare gas to power project to date in the Middle East
Aggreko is proud to announce we have completed commissioning of the largest flare gas to power project in the Middle East to date at 165 MW capacity. The plant is situated nearby the Saqala Field, Garmain block, South East Kurdistan.
The 165 MW modular power plant has run at full capacity for 72 hours in the project’s final site acceptance test (SAT), marking successful on-time, on-budget delivery. The plant is run on approximately 40 million square cubic feet (SCF) per day of associated petroleum gas (APG) from the Saqala Field, saving 840 tonnes of CO2 per day, and cutting flaring by a third.
Delivered over the course of 2020-2021 against the backdrop of the pandemic, the project was conceived and executed in close collaboration with Kurdistan’s Ministry of National Resources (MNR) and Ministry of Electricity (MOE).
Aggreko also delivered a new 6km gathering pipeline to transport the APG to the power plant, and upgraded 7km of 33 kV and 33km of 132 kV overhead cables to new high tensile low sage (HTLS) conductors in order for the local distribution grid to handle the new power plant’s full output.
Ahmed Mufti, Kurdistan Regional Government’s Deputy Minister of Natural Resources (MNR) said, “We worked with Aggreko to provide a creative solution to convert flare gas to power in a way that directly benefits the local population and the regional in general, while creating a positive environmental impact and improving air quality."
Phil Burns, Managing Director for Aggreko Middle East, comments: “Kurdistan’s Regional Government has been forward-thinking in looking for ways to capture and convert gas that would otherwise be flared, to unlock production and power the local economy. We are extremely proud to have worked with the Ministries to deliver the Middle East’s largest flare gas to power project to date, while upgrading the local infrastructure to the lasting benefit of the community and businesses it serves.”
The project is now contracted to run for four years, delivering power 24/7/365. Built using 192 MW of modular gas generators, the plant can easily be scaled up or down in response to changing gas volumes. Approximately 60 Aggreko engineers have delivered the project, with 80 local jobs created directly and indirectly for the site's delivery and ongoing operation, including 44 local nationals who have already commenced Aggreko's official training scheme.
News Category:
-
TotalEnergies to cease operating its oldest steam cracker in Antwerp
TotalEnergies’ Antwerp platform provides an update on its investments for the future and announces plan to reconfigure its petrochemicals operations to strengthen competitiveness. ...
23-04-2025
-
HOERBIGER to break ground on new Florida Campus in Florida
HOERBIGER Corporation of America will hold a ceremony to commemorate the groundbreaking of its future home, the HOERBIGER Florida Campus, on Wednesday, April 23rd. Construction ...
22-04-2025
-
Amogy and JGC to accelerate commercialisation of ammonia cracking catalyst
Amogy, a provider of mature, scalable, and efficient ammonia-to-power solutions, today announced the first pilot plant deployment of its advanced ammonia cracking catalyst ...
17-04-2025
-
Clariant teams up with Technip to introduce new steam-to-oil catalyst
Clariant, a global leader in specialty chemicals, today announced the launch of StyroMax UL-100, its most advanced ethylbenzene dehydrogenation catalyst to date. This ...
09-04-2025
-
Yokogawa Launches OpreX Plant Stewardship
Yokogawa Electric Corporation announces the launch today of OpreXTM Plant Stewardship, the most comprehensive lifecycle service program in the company’s OpreX Sustainable ...
08-04-2025
-
IndianOil to build mega petrochemical project in Paradip
In a landmark development, Indian Oil Corporation Ltd. (IndianOil) signed a Memorandum of Understanding (MoU) with the Government of Odisha to set up a world-class Petrochemical ...
08-04-2025
-
BDI BioEnergy to begin construction of biofuel feedstock refinery plant
BDI-BioEnergy International has signed a contract with Ghent Renewables BV to begin the construction of a pioneering biofuel feedstock refinery plant. This facility will ...
04-04-2025
-
Lummus Technology completes startup of electric heater demonstration unit
Lummus Technology, a global provider of process technologies and value-driven energy solutions, announced the successful startup of its SRT-eTM commercial demonstration ...
03-04-2025
-
Clariant announces the successful startup of MegaMax™ 900 catalyst
Clariant, a sustainability-focused specialty chemical company, today announced the successful startup of its MegaMax 900 methanol synthesis catalyst at European Energy’s ...
03-04-2025
-
Burckhardt Compression, a global leader in reciprocating compressor technology, has won a significant order for Digital Monitoring Services in Saudi Arabia. The order ...
03-04-2025