31-07-2012

Valero 3Q & 4Q turnaround schedule

Valero has updated its maintenance turnaround schedule.  This list includes only major projects that will have a material impact on production, and it is subject to change.  While we provide general guidance on the start and duration of the maintenance, we do not disclose specific beginning and end date.

Refinery        Unit       Month      Approx duration
Houston        FCC      Sep          8 weeks
Pembroke     Crude    Oct          8 weeks

Sponsor:

News Category:

Other News Items

  • Responsive image Better analyses. Better decisions.
  • Responsive image Chemical Treatments
  • Responsive image Level and density in FCC processes
  • Responsive image Smart solutions for valves and valve automation
  • Responsive image Ejector Systems
  • Responsive image FCC catalyst solutions
  • Responsive image 6 - 8 May 2025,
    Dubai, UAE
  • Responsive image FCC Refining Catalysts
  • Responsive image Top Performer in Portable Fuel Analysis
  • Responsive image Solve the Industrial Data Problem