Refinery operations go on stream

Hon’ble High Court of Karnataka has passed an order to draw 2 MGD water from Nethravathi river on 25 April’12. District Commissioner of Mangalore District has agreed to supply water @ rate of 5 MGD with immediate effect as the Thumbe dam on Nethravathi river is overflowing to sea. Formal consent from DC office is awaited.

Refinery has already commissioned CCR I and CDU II. Commissioning of Hydrogen generation unit, Hydrocracker unit I, Gas oil hydrodesulphurization unit (GOHDS) and CCRII commissioning has been started and expected to be on stream by 28th April’12.

Commissioning of Phase III expansion units will be kept on hold till the increase in water supply @ 8.5 MGD is sanctioned by the GoK. The planned shutdown of Hydrocracker II for 45 days and other associated units will continue and shall be completed by May end. 

Sponsor:

News Category:

Other News Items

  • Responsive image Better analyses. Better decisions.
  • Responsive image 6 - 8 May 2025,
    Dubai, UAE
  • Responsive image FCC catalyst solutions
  • Responsive image FCC Refining Catalysts
  • Responsive image Level and density in FCC processes
  • Responsive image Ejector Systems
  • Responsive image Smart solutions for valves and valve automation
  • Responsive image Solve the Industrial Data Problem
  • Responsive image Chemical Treatments
  • Responsive image Top Performer in Portable Fuel Analysis