Valero 1Q & 2Q Turnaround Schedule Update

Valero has updated its maintenance turnaround schedule. This list includes only major projects that will have a material impact on production and is subject to change.  While we provide general guidance on the timing and duration of the maintenance, we do not disclose specific beginning and end dates.
    
Refinery            Unit                     BPD         Month     Days
Port Arthur         FCC/Alky             79,000     Jan.         44
Corpus Christi   E. Plant HCU       15,000      Jan.         18
St. Charles        Crude/Coker*      190,000    Feb.         30
Corpus Christi   W. Plant HCU      36,000      March     18
Port Arthur        Hydrocracker       45,000      March      38
Memphis           Crude/FCC/Alky  105,000     March     45

* Plantwide outage

Sponsor:

News Category:

Other News Items

  • Responsive image Top Performer in Portable Fuel Analysis
  • Responsive image Chemical Treatments
  • Responsive image Level and density in FCC processes
  • Responsive image Better analyses. Better decisions.
  • Responsive image FCC Refining Catalysts
  • Responsive image Ejector Systems
  • Responsive image Solve the Industrial Data Problem
  • Responsive image Smart solutions for valves and valve automation
  • Responsive image FCC catalyst solutions
  • Responsive image 6 - 8 May 2025,
    Dubai, UAE